Integrated Master Plan · Concept v2.5 · Horizon 2032

Uz Silicon Tech
The Full Value Chain

From mining to finished product — quartz mine · metallurgical silicon · polysilicon · wafer · closed-loop waste recovery (ZLD + STC) · ~1 GW firm power · workforce and education system. Analysed through eight expert lenses.

Initiator: Kuziev Mumin Ulashboevich Location: Navoi / Jizzakh / Sirdarya Status: Pre-Feasibility concept
100 kt
Polysilicon/yr · target
20 GW
Wafer/yr · proposed
~1 GW
Firm power
~2,800 ha
Total land
~6–8 k
Direct jobs
01

Value chain — overview

Geologist · Process Eng.

The project is not a single plant but a fully vertically integrated cluster: quartz is mined, purified stage by stage, and processed all the way to wafer. Every waste stream is recovered in closed loops. Uzbekistan's advantage is precisely here: Oman imports its raw material — we take ours from the ground.

Stage 0Quartz mineSiO₂ 98.7% · Nurota/Jerdanak
Stage 1MG-SiArc furnace · 98–99% Si
Stage 2TCS synthesisSiHCl₃ + H₂/HCl
Stage 3DistillationPurify → 9–11N
Stage 4PolysiliconSiemens CVD · 6N+
Stage 5WaferIngot → slicing
Closed loop: STC → TCS hydrochlorination · H₂ and HCl recovery · ZLD water system · kerf (cutting waste) recovery — zero liquid discharge.
02

Geology and mining

Geologist

The geologist's view: domestic quartz is no longer an assumption. The Tashkent Institute of Chemical Technology (Nomazov & Aripova, 2025) measured the composition of quartz from Uzbek deposits:

SourceSiO₂Al₂O₃Fe₂O₃Assessment
Nurota vein quartz98.74%0.45%0.02%High purity
Jerdanak quartzite97.72%0.77%0.12%Illite admixture

✓ What is confirmed

The SiO₂ grade is sufficient for MG-Si (metallurgical silicon). Uzbekistan has 20+ quartz deposits and beneficiation experience (JSC "Kvarts"). This is a real advantage against Oman's "import dependency" weakness.

Official strategic recognition: Uzbekistan's Critical Elements list includes silicon (Si) and high-purity silica/quartz — with vast, largely untapped potential (Mirkamalov et al., 2025). That is, the state recognises this material as strategic.

✗ Still required for Gate-1 — and the JORC question

Today we have chemical composition (TKTI), but no JORC-compliant resource statement. Uzbekistan uses the GKZ (Soviet) classification, but international investors (IFC, banks) require a resource statement to the JORC or NI 43-101 standard: tonnage + grade + confidence category (measured/indicated/inferred). Only a drilling programme delivers this.

Gate-1 Resource Assessment — full checklist

ItemRequirementStatus
Candidate depositsJizzakh · Navoi · Sirdarya + Nurota/Jerdanak⚠ To select
SiO₂ range≥98% (confirmed for MG-Si: 97.7–98.7%)✓ Have
Boron (B) + phosphorus (P) ppmMost critical for polysilicon — not yet measured✗ Needed
Post-beneficiation purityDoes it reach 6N (pilot test)✗ Needed
30-year reserve~9 Mt quartz (JORC-compliant)✗ Drilling
Mining cost$/tonne → confirm the $1.3/kg feedstock estimate✗ Needed

Signal to UzSIF / Geology committee: "We hold scientifically confirmed initial evidence; we are ready to begin Gate-1 (drilling + B/P + JORC)."

B/P — the most critical parameter

For polysilicon, boron (B) and phosphorus (P) are the most important, because they corrupt the semiconductor property and are extremely hard to remove from quartz.

ElementTarget (indicative)Method
Boron (B)< 0.1 ppmICP-MS
Phosphorus (P)< 0.3 ppmICP-MS

No B/P measurement currently exists for any Uzbek deposit — this is normal. Only an ICP-MS lab + international assay + JORC expert can establish it. Final polysilicon spec is even tighter (ppba level).

Pilot beneficiation test (6N potential)

After beneficiation, Al₂O₃, Fe₂O₃, TiO₂, CaO, MgO must drop to ppm levels. Pilot test stages:

Drilling programme (for JORC)

ParameterMinimum (indicative)
Drill holes~12 (more possible depending on deposit size)
Depth150–200 m
Output3D geological model · tonnage + grade + confidence category
Duration~6 months · certified by a JORC expert

Gate-1 deliverables

◆ Official signal to government (executive sentence)

"According to preliminary scientific data, the Jizzakh and Navoi regions hold promising quartz resources for a polysilicon industry. Their suitability must be confirmed through independent laboratory assay, drilling and a JORC audit."

⚠ Geological accuracy (Engineering DD safeguard)

Only confirmed high-purity quartz is presented as the feedstock base: Nurota vein quartz (98.7%) and Jerdanak quartzite (TKTI). Uzbekistan has a broad mineral base, but silica sand ≠ polysilicon quartz, and each deposit (e.g. Jeroy — a phosphorite deposit, not polysilicon) must be verified separately. Maintaining this distinction preserves credibility before the geology committee.

03

Process technology

Process Eng. · Eng. DD

From quartz to polysilicon there are 5 chemical-physical stages. Each requires distinct equipment, energy and a safety regime.

StageProcessMain equipmentEnergy (kWh/kg)
1 · CarbothermicSiO₂ + 2C → Si + 2CO (1800°C)Submerged arc furnace (SAF)~11–13
2 · TCS synthesisSi + 3HCl → SiHCl₃ + H₂Fluidized-bed reactor~5
3 · DistillationFractional purification (remove B, P, metals)Distillation columns~8
4 · Siemens CVDSiHCl₃ + H₂ → Si (1100°C, grows on rods)Siemens reactors (CVD)~45–50
5 · Crushing/packingCrushing, quality control, packagingClean room, automation~2
Total (to polysilicon)~70–75

◆ Process-engineer note: 6N vs 11N

The base target is solar-grade 6N (99.9999%) — for solar panels. Semiconductor-grade 11N (microchips) is an entirely different, far more complex level; only 5 companies manage it (Wacker, Hemlock, OCI, Tokuyama, Mitsubishi). It is left as a later, separate phase.

⚠ Eng. DD: technology owner and power quality

Who is the licensor/EPC? The Siemens process and STC closed loop require know-how (Western options: centrotherm and others). Power quality: a Siemens reactor cannot tolerate even a one-second interruption — this makes firm baseload power mandatory in the energy system.

04

Waste: ZLD + closed-loop STC

Process Eng. · Govt (ESG)

This is the heart of the project's ESG / "low-carbon" certification and what the EU buyer demands. The two main waste streams of the polysilicon process — silicon tetrachloride (STC, SiCl₄) and wastewater — are fully recovered.

STC → TCS recovery~96%
Hydrogen (H₂) recovery~99%
HCl reuse~90%
Water reuse (ZLD)~98%

Three closed loops

◆ Government/ESG view

ZLD + closed-loop STC raises capex by ~10–15%, but it: (1) solves water scarcity, (2) earns the "green" certificate (EU premium condition), (3) lowers operating cost by reducing chlorine/feedstock purchases. Oman built exactly this system.

05

Wafer plant

Process Eng. · Market

The wafer stage is built in Uzbekistan by a Turkish partner. Polysilicon → ingot → wafer. This is your product's adjacent, immovable buyer.

StageProcessWaste recovery
Ingot growthCzochralski (CZ) — monocrystal pullingPot remnant → re-melt
SlicingThin wafers via diamond wire sawKerf loss (cutting powder) → recovery
Wash/sortCleaning, quality control, packagingConnects to the ZLD water system
06

Offtake map (buyers)

Market · Inv. bank

The 100kt of polysilicon splits in two and reaches the EU via wafer. This is the project's clear answer to "who buys it?"

SourcePolysilicon100 kt/yr
Buyer A · in UZTurkey wafer (20 GW)~50 kt → wafer
Buyer B · exportIndia~50 kt polysilicon
End marketEurope (EU)wafer · duty-free
End marketIndia waferWaaree·Tata·ReNew
BuyerVolumeWhy themMargin* (all-in $7.8/kg)
🇹🇷 Turkey wafer (in UZ)~50 ktAdjacent · non-China · Turkey–EU customs unionpremium
🇮🇳 India~50 ktBuilding 20+ GW wafer, ~zero domestic polysilicon, ALMM policy+$2/kg (thin)
🇪🇺 Europe (via wafer)~63 GW/yr demand; €2.2 bn EU programme+$12/kg
🇺🇸 USA (optional)UFLPA/FEOC mandate non-China+$16/kg

*Margin from the Energy-Cost model (separate Excel file). India is price-sensitive; US/EU premiums are wider.

◆ Market expert

The non-China premium is real but the window is narrow — Oman (100kt), Qatar and the US are filling it. The adjacent Turkey wafer plant + India offtake keep you in this race. An early LOI/MOU turns "demand" into "a buyer".

07

Energy supply

Power · Inv. bank

The full chain (MG-Si + polysilicon + wafer) requires ~1 GW of firm (continuous) power — ~8,800 GWh per year. ACWA Power / Masdar IPP model: they build it, you buy via a 20–25 year PPA.

Solar (PV)~1.2 GW
Wind~600 MW
Gas (firm backup)~500 MW
BESS (storage)~300 MW
MetricValueNote
Firm power (full chain)~1 GWMG-Si + poly + wafer
Electricity cost~$2.6–2.8/kgBetter than grid $4.4; above China $1.65
Energy cluster capex~$2.5–3 bnOwned by ACWA/Masdar (PPA)
CO₂ footprint~14 kg/kgWithin "low-carbon" range (China ~36)

◆ The core trade-off + Excel companion

More gas = cheaper/firm, but higher CO₂ (weakens the premium). More renewables = clean, but higher capex. This balance is computed in a separate Energy-Cost Excel model — varying the gas/renewable share shows $/kg cost, firm-coverage % and CO₂ footprint in real time.

08

Land and infrastructure

Geologist · Eng. DD

Total area ~2,800 hectares — mostly the solar farm. Industrial core ~600 ha.

Solar farm ~1,800 ha
Wind zone (spacing) ~500 ha
Polysilicon + MG-Si plant ~250 ha
Wafer plant ~120 ha
Gas/BESS/substation ~40 ha
ZLD/water/logistics/buffer ~90 ha

Location factors: Navoi — Masdar solar experience, industrial zone, but water-scarce (ZLD mandatory). Jizzakh/Sirdarya — water/logistics may be better. Final choice assessed by proximity to the quartz mine + energy + water + rail connection.

09

Human capital (workforce)

Govt · Operations

The full cluster generates ~6,000–8,000 direct jobs (2–3× more indirect). The largest need is at the wafer plant.

Wafer plant~3,500
Polysilicon + MG-Si~1,400
Lab/QC/utilities/ZLD~450
Admin/logistics/management~500
Mining~300
Energy cluster O&M~200
LevelRoleField
Engineer / PhDProcess, R&D, qualityChemical engineering · metallurgy · materials science · power
TechnicianEquipment, automation, maintenanceInstrumentation · mechanical · electrical
OperatorFurnace, reactor, CZ, slicingChemical operators · clean room
HSE / environmentalSafety, ZLD, chlorine chemistryIndustrial safety · environment
10

Education and workforce training

Govt · University

The most critical timing factor: training must start in 2028–29, not in 2032. If it does not begin 3–4 years ahead, there will be no qualified workforce when the plant commissions.

University departments (partners)

InstitutionFieldRole
Tashkent Inst. of Chemical Technology (TKTI)Chemical engineering, quartz beneficiationCore partner (the quartz study came from here)
Navoi State Mining & Tech UniversityMining, metallurgyMG-Si and mining workforce
Tashkent State Technical UniversityPower, automation, mechanicsTechnicians and engineers
Turin Polytechnic (Tashkent)Materials science, mechatronicsInternational-standard engineers
Foreign partner (Germany/Korea)Siemens process, CVD know-howMentorship, internship, licensing

Training schedule

Phase2026202720282029203020312032
Curriculum + department
Scholarships + 1st cohort
Overseas internship (engineers)
On-site training centre + simulator
Vendor training (equipment)

◆ Practical approach

1) Send the first wave of engineers in 2028–29 to plants in China/Korea/Germany for hands-on training (the fastest route). 2) Build an on-site training-simulator centre. 3) Training contracts with equipment vendors. 4) Redesign university programmes to fit real needs.

11

CAPEX breakdown (detailed)

Auditor · Inv. bank

The first table UzSIF asks for. Each stage separately, with owner and model. Note: wafer and energy are carried by partners (Turkey, ACWA/Masdar), so Uz Silicon Tech's own capex is ~$4.5–5.5 bn.

ComponentCapex (preliminary)Owner / model
1 · Quartz mine~$0.1–0.2 bnUz Silicon Tech / state
2 · MG-Si (arc furnace)~$0.4–0.5 bnUz Silicon Tech
3 · TCS synthesis~$0.5–0.7 bnUz Silicon Tech
4 · Distillation (purification)~$0.5–0.7 bnUz Silicon Tech
5 · CVD (Siemens reactors)~$1.8–2.2 bnUz Silicon Tech (largest)
6 · ZLD + closed-loop STC~$0.4–0.6 bnUz Silicon Tech
7 · Land + infrastructure~$0.3–0.5 bnUz Silicon Tech / state
Your portion (1–7)~$4.5–5.5 bnUz Silicon Tech
8 · Wafer plant (20 GW)~$2.0–4.0 bn🇹🇷 Turkey partner (JV)
9 · Energy cluster (~1 GW)~$2.5–3.0 bnACWA/Masdar IPP (PPA)
TOTAL CLUSTER~$9–12.5 bnMulti-party

◆ Important for the auditor

"$1.5–2 bn" (v1.0) is outdated. The fully integrated cluster is ~$9–12.5 bn. But due to the asset-light structure your balance sheet is ~$4.5–5.5 bn — the rest is off-balance via partner/PPA.

Polysilicon plant CAPEX structure (industry-typical)

For the polysilicon core only (TCS→CVD), ~$3.6–4.2 bn. MG-Si, wafer and the energy cluster are outside this.

TCS + Distillation~32%
Siemens CVD~28%
Utilities (power/water/gas)~22%
STC loop + ZLD~10%
EPC / Engineering~8%

★ Global benchmark: Oman (United Solar Polysilicon)

The world's largest non-China polysilicon plant — the proven template for our project:

  • 100kt · ~$1.6 bn → ~$16,000/tonne · built in ~22 months
  • Financing: IFC $480M + OIA sovereign fund $260M + Waaree + local banks
  • FEOC-compliant · ESG · ZLD · free zone · on-site solar
  • Its weakness: it imports raw material — we overcome this with domestic quartz + MG-Si

Signal to investors: "Oman built 100kt for $1.6 bn, financed by the IFC + a sovereign fund. We replicate the same model, with a domestic-feedstock advantage."

Note: Oman figures are from confirmed public sources. The CAPEX percentage structure is an industry-typical estimate, not any company's internal number.

12

Shareholding structure

Fund director · Inv. bank

An investor's first question: "who owns it?" This is the indicative cap table of the polysilicon company (SPV). Note: energy (ACWA/Masdar) and wafer (Turkey) are separate vehicles; they are primarily contractual partners (PPA / offtake), with optional minority stakes.

UzSIF (sovereign fund, anchor) ~30%
Strategic industrial partner ~25%
DFI / IPO / private investors ~25%
Partners minority (ACWA/Turkey, opt.) ~20%

Percentages indicative. Core principle: the state/sovereign fund as anchor (Oman/OIA model), a DFI (IFC) with debt+equity, a strategic industrial partner bringing technology.

13

Financial model + sensitivity

Auditor · Inv. bank

Revenue model (100kt): price × volume. Cost from our Energy model — cash ~$5.8/kg, all-in ~$7.8/kg.

Polysilicon priceRevenue/yrEBITDAEBITVerdict
$12/kg (blended premium)$1,200M$620M$420MStrong
$10/kg$1,000M$420M$220MHealthy
$8/kg$800M$220M$20MBreak-even
$6/kg (China price)$600M$20M−$180MLOSS

⚠ Sensitivity — the most important truth

The all-in break-even point is ~$7.8/kg. At the Chinese commodity price ($6) the project makes a loss. So the project works only in premium markets ($10+/kg, FEOC/EU) — not in price competition with China. This is the financial proof of the entire "non-China" strategy.

Payback (your ~$5 bn portion): ~8 years at $12/kg · ~12 years at $10/kg. Acceptable for an infrastructure project.

All figures are linked to the Energy-Cost model. Final IRR/NPV is computed in the Feasibility Study with the full financing structure.

14

SWOT analysis

Strategic
S · Strengths
Domestic vertical chain

Quartz+MG-Si in-house (not in Oman) · cheap renewable potential · neutral geopolitics · state support · non-China/FEOC position.

W · Weaknesses
Logistics + cost

Landlocked · gas-heavy grid (ESG tension) · no polysilicon experience/workforce · all-in cost above China · subscale risk below 100kt.

O · Opportunities
De-China demand

EU/US diversification · India wafer boom (needs polysilicon) · 2028–30 rebalancing · semiconductor ecosystem.

T · Threats
Non-China oversupply

Oman/Qatar/US/Morocco · premium compression · China price war · gas deregulation · 4-party coordination.

15

Strategic impact for Uzbekistan

Govt · Presidential Admin.

For the Presidential Administration and the Cabinet of Ministers — national-level outcomes:

6–8 k
Direct jobs
$1+ bn
Annual revenue
~1 GW
New renewables
1st
Polysilicon in C. Asia
16

Gate-1 → FID timeline

Inv. bank · UzSIF

The most important view for investors: which stage when, and which "gate" stops the project if not passed. Without passing Gates 1–3, there is no FID.

Phase2026202720282029203020312032
Gate-1 Resource (JORC,B/P)
Gate-2 Market (LOI)
Gate-3 Energy (PPA)
Gate-4–5 Feasibility
Gate-6 Offtake lock
Gate-7 FID ★
Construction
Production ★

FID ~end of 2028 → construction ~3–4 years → production in 2032, aligned with the rising demand/shortage cycle.

17

Who this document is for

The master plan is intended for four groups — each reads a different section.

★ Primary target
UzSIF — Uzbekistan Sovereign Fund

Expects exactly this kind of document. Signal: "we are ready, you start Gate-1 and be the orchestrator." Capex + Gate timeline + offtake are for them.

Technical validation
Geology committee

The geology section is in the right tone: "we have an assumption, you confirm with JORC." B/P, reserves, drilling are for them.

Energy partner
ACWA Power / Masdar

The energy section and ~1 GW firm requirement matter most to them. PPA model + 2 anchor buyers give them bankability.

Wafer partner
Turkish wafer manufacturers

20 GW wafer → 50 kt adjacent non-China polysilicon + Turkey–EU customs route = a golden opportunity for them.

18

Eight-expert verdict

Fund director
Differentiator + sponsor

Vertical integration (domestic quartz) is a real moat. But "who puts in equity?" is still unanswered. A sovereign fund must anchor it.

Market expert
Premium real, window narrow

Non-China demand exists, but Oman/Qatar/US are filling it. The adjacent Turkey wafer + India offtake are a strong position.

Government expert
National strategic cluster

~1 GW new power + 6–8k jobs. State orchestration and an energy guarantee are decisive.

Investment bank
2 offtakes required

Energy PPA + polysilicon offtake — without both it is not financed. The IFC model (Oman) exists.

Financial auditor
Capex $8–12 bn

"$1.5–2 bn" is outdated. All-in cost is above China — the business relies on the premium market, not price competition.

Engineering DD
Technology + power quality

Who is the licensor/EPC? The reactor cannot tolerate interruptions → firm power mandatory. ZLD/STC raise capex.

Geologist
Quartz yes, B/P unknown

SiO₂ confirmed for MG-Si. Boron/phosphorus measurement and reserve estimate are the rest of Gate-1.

Process engineer
5 stages + closed loop

The process is known and proven. 6N is the target; 11N a later phase. STC closed-loop + ZLD is the right approach.

19

Risks and honest caveats

⚠ The biggest risk — coordination, not technology

Four independent mega-decisions (poly · wafer · energy · offtake) must be signed at the same time. Only a state/sovereign fund as orchestrator can break this.